Project update: West Ryde showroom

The team has made tremendous progress at our Kia and BYD showroom project in West Ryde, with the structural steel frame now installed, ready for roofing. This marks a major milestone for the team following weeks of careful planning the methodology and installation of engineered shoring props to safely support the loads of the mobile crane on the existing suspended structure during the installation of the structural steel.

Over the next few weeks, the team will install the roof sheeting, light-steel framing for the facade and interior for the brand-new dealership.

We are excited to continue our long-standing relationship with Centric Architects on another automotive project.