Stage 1
This project required initial decontamination of an old petrol station site, to allow construction of 3-storey TAS building with underground carpark, involving; metal and wood technology rooms, domestic and commercial food technology rooms, acoustic music rooms and other TAS related learning areas, linkways to existing buildings and external works.

Stage 2
Construction of two buildings both linking to the existing school, was carried out concurrently on opposite sides of the school whilst the school was fully operational. Building 1: a new 2-storey administration building was integrated with the existing heritage convent. Building 2: refurbishment and extension of a 3-storey building containing the library and GLA’s.