Project Update – Campion College, Toongabbie

Some updated progress shots for the new library and student house dwellings at Campion College, Toongabbie. Our Sydney major works team has managed the installation of internal framing, roof tiles and external brickwork to houses 3, 4, 5 and 6.

On the larger building, works to the library have included the pouring of the level 1 slab and the commencement of formwork for the roof slab. The next 2 weeks will see the library roof concrete slab completed and internal works on the houses continuing. 

We are working with Project Strategies and WMK Architecture on this project. This project is due for completion in early 2023.