Project Update

Project Update
January 17th, 2025
Project update: Alto Castle Hill

It’s fantastic to be back on-site after our Christmas and New Year break! The team has returned refreshed and ready to go. Since our last project update, we’ve made significant progress at Alto Castle Hill, where the transformation of the...

Project Update
December 13th, 2024
Project update: Australian International Academy – Stage 4, Kellyville

The team are making great progress with the new senior building project at Australian International Academy in Kellyville. We have recently poured the ground floor slab and installed the precast arches. For the rest of the year, the team will...

Project Update
November 29th, 2024
Project update: Multi-Purpose Learning Space – New Hope Christian School, Dural NSW

Our Sydney RFM has been awarded the contract to build a new multi-purpose learning space at New Hope Christian School in Dural. Over the past few weeks, the team has completed the groundwork, poured the concrete slab, and is now...

Project Update
November 28th, 2024
Project update – Stage 1 Complete: Norwest Christian College, Riverstone

Our Sydney Major Works team is pleased to have recently completed and handed over Stage One ( of three stages ) to the school. The undercroft development includes specialist classrooms equipped with state-of-the-art hospitality appliances and equipment, providing significant benefits...

Project Update
November 6th, 2024
Project update: Cupra, Smeaton Grange

The new Cupra showroom at Smeaton Grange is making excellent progress, with the structural steel, metal roof sheeting, and roof insulation nearly finished. The team is now putting the finishing touches on the roof, while service rough-in work on the...

Project Update
October 28th, 2024
Project update: Trinity Catholic College, Auburn

The school community at Trinity Catholic College in Auburn recently enjoyed a first look at the impressive new facade, now visible as the scaffolding has been removed. This milestone marks a key step in the college’s ongoing transformation, which aims...

Project Update
October 14th, 2024
Project update: Norwest Christian College – McCullouch Extension (Stage 2), Riverstone

Today marked the final major concrete pour at Norwest Christian College in Riverstone, as part of the McCullouch Extension (Stage 2). The team successfully completed the suspended concrete deck, paving the way for new staff administration areas, a textile classroom,...

Project Update
September 30th, 2024
Project update: Australian International Academy – Stage 4 Senior Building, Kellyville

The new senior building at the Australian International Academy in Kellyville is progressing well. Bulk and detailed earthworks have recently begun, along with the relocation of existing services and the installation of new ones. In the coming months, the team...

Project Update
September 27th, 2024
Project update: Alto Castle Hill

In recent weeks, our team at the Alto Castle Hill project has begun on-site works. They are currently carrying out further demolition of the existing industrial facility, as well as bulk earthworks for future car parking and landscaping for the...

Project Update
September 20th, 2024
Project update: Norwest Christian College, Riverstone

Great job to the team at Norwest Christian College in Riverstone! Yesterday, they efficiently managed the concrete pour for the new basketball court during the busy morning drop-off. Thanks to clear communication between the traffic management team and those on-site,...

Project Update
August 28th, 2024
Project update: Green Point Christian College, Green Point

The administration building at Green Point Christian College is progressing well, with the structural steel roof recently completed. The team is now installing roof insulation and metal roof sheeting, with the rough in works to the ground floor having also...

Project Update
August 19th, 2024
Project update: Buckland Cafe, Springwood

The Sydney RFM team has begun the demolition of the former Boiler House Building to make way for a brand-new resident café and shop. Externally, the team is meticulously reclaiming bricks from the demolition to be reused in the café,...

Project Update
August 16th, 2024
Project update: Peugeot Dealership, Artarmon

Our Sydney RFM team has begun demolition at the site for the new Peugeot dealership in Artarmon. In the coming weeks, the team will start framing and installing structural steel for the new sales area and corporate signage, with the...

Project Update
July 29th, 2024
Site meeting & Project update at King Living, Balgowlah NSW

Our Sydney teams gathered this morning for a construction meeting and a detailed site walkthrough of the exciting progress at our King Living project in Balgowlah. The first stage of demolition is complete, and we’re making great strides with the...

Project Update
July 1st, 2024
Level One concrete pour – Green Point Christian College

The major pour of the Level one slab was completed last friday at Green Point Christian College in Green Point. The team sucessfully coordinated over 33 trucks delivering the concrete supplied throughout the course of the busy school day. This...

Menu