Project Update

Project Update
August 28th, 2024
Project update: Green Point Christian College, Green Point

The administration building at Green Point Christian College is progressing well, with the structural steel roof recently completed. The team is now installing roof insulation and metal roof sheeting, with the rough in works to the ground floor having also...

Project Update
August 19th, 2024
Project update: Buckland Cafe, Springwood

The Sydney RFM team has begun the demolition of the former Boiler House Building to make way for a brand-new resident café and shop. Externally, the team is meticulously reclaiming bricks from the demolition to be reused in the café,...

Project Update
August 16th, 2024
Project update: Peugeot Dealership, Artarmon

Our Sydney RFM team has begun demolition at the site for the new Peugeot dealership in Artarmon. In the coming weeks, the team will start framing and installing structural steel for the new sales area and corporate signage, with the...

Project Update
July 29th, 2024
Site meeting & Project update at King Living, Balgowlah NSW

Our Sydney teams gathered this morning for a construction meeting and a detailed site walkthrough of the exciting progress at our King Living project in Balgowlah. The first stage of demolition is complete, and we’re making great strides with the...

Project Update
July 1st, 2024
Level One concrete pour – Green Point Christian College

The major pour of the Level one slab was completed last friday at Green Point Christian College in Green Point. The team sucessfully coordinated over 33 trucks delivering the concrete supplied throughout the course of the busy school day. This...

Project Update
May 8th, 2024
Project update: Trinity Catholic College, Auburn

Stage 1 works are well underway at Trinity Catholic College, Auburn. The last few months have seen demolition works to the facade, classrooms in Block D and now the team has commenced ceiling and wall framing, service rough-ins and foundations...

Project Update
March 22nd, 2024
Project update: Blaxland Reformed Church

Designed by Alan Powell Architecture, it is great to see the progress at Blaxland Reformed Church.  Internal works are progressing well with the internal fit-out well underway.  External works and landscaping are due to commence on site next week as...

Project Update
February 21st, 2024
Project update: St Joseph Catholic Primary School, Rosebery

Our team is making significant progress with the construction of the new school campus at Rosebery. Over the past few weeks, the project team has successfully coordinated various trades, such as electrical, joinery, fitout works for the hall and classrooms,...

Project Update
February 5th, 2024
Project update – Allan Border Oval Pavillion, Mosman

Great to see the progress at the Allan Border Oval Pavilion project in Mosman. The pavilion and grandstand will include ground floor change rooms, public toilet amenities, groundkeeper/storage facilities and a kiosk while first floor facilities, accessible via a lift, will include...

Project Update
January 29th, 2024
Project update: Gilroy Catholic College, Castle Hill

Gilroy Catholic College located in Castle Hill, is undergoing a large redevelopment of its existing campus. Designed by Stanton Dahl Architects, Reitsma Constructions is completing the project on behalf of the Catholic Schools Parramatta Diocese (CSPD). Project Management is being...

Project Update
January 19th, 2024
Motorserve Wollongong

Last week marked the commencement of the new service workshop fit-out project in Wollongong. This is the first project working together with Motorserve. The project encompasses a 900m2 workshop fit-out, featuring staff amenities and service reception areas. We look forward...

Project Update
December 1st, 2023
Project update: Wollongong Mazda

The all new Wollongong Mazda is starting to take shape with the structural steel and cladding to the façade is in its final stages. The team have scheduled the roof installation to the workshop and complete internal lining and finishes...

Project Update
November 10th, 2023
Project update: St Joseph Catholic Primary School, Rosebery

The school community got the first glimpse of the new facade at St. Joseph Catholic Primary School in Rosebery as a portion of the scaffolding has been removed. A key feature of the curved facade is the recycled brickwork which...

Project Update
May 3rd, 2023
Project update – Gilroy Catholic College, Castle Hill

Works have commenced at Gilroy Catholic College located in Castle Hill. Reitsma is executing the project on behalf of the Catholic Schools Parramatta Diocese, marking the third project at the school for Reitsma. We are honoured to collaborate with the...

Project Update
March 17th, 2023
Project Update – Buckland Aged Care Services, Stage 6,7,8 & Heritage Cottage

The multistage project for Buckland Aged Care Services in Springwood, designed by Integrated Design Group, has seen solid progress under Reitsma’s management. We are delighted to announce the successful completion of stages 6, 7, 8, and Heritage Cottage, which now...

Menu