Project Update
Project update – Kennards Cardiff
Construction is continuing well for the new proposed Kennards self storage at Cardiff. The structural steel roof structure and epoxy flooring have been finished, while external cladding, sarking, and internal fitout works are still in progress. Great progress by the...
Project update – Kloster Ford Dealerships
Our Newcastle Major works team has collaborated with EJE architecture and Tony White Group to achieve significant progress in the Kloster Facilities projects situated at Cardiff and Rutherford. In recent weeks, the team has undertaken internal structural steel, footings and...
Project Update – McCarrolls Volkswagen Service Centre, Waitara
Great progress is being made on the new service centre at McCarrolls Volkswagen, Waitara. So far the project has involved bulk excavations with formwork and steel fixing. Concrete footings have been poured with shotcrete being used to reinforce the walls. The...
Project update – St Joseph’s Catholic Primary School Rosebery
The construction of St. Joseph’s Catholic Primary School in Rosebery, Sydney, is moving forward on schedule despite some of the weather challenges of 2022. The foundation structure has been largely completed and work on the ground floor has commenced at...
Project update – St George Christian School, Hurstville
Located in the middle of a busy operating school, our Sydney Major works team has achieved great progress recently at St George Christian School, Hurstville. The structural steel roof structure is currently being erected whilst service rough-in and wall framing...
Project Update – Imagine Learning Centre, Nowra
Works are progressing well for the new Imagine Learning Centre at Nowra. ( Our second Imagine Centre in the Nowra region ) Last week the ground floor slab was poured with structural framing works taking place for the remainder of...
Project update – Campion College Toongabbie ( Library & Houses 3,4,5 & 6 )
Great progress has been made at Campion College, Toongabbie over the last couple of months. Masonry and tiling on houses 3, 4, 5 and 6 has been completed with internal linings ongoing. Masonry and services rough-in is proceeding throughout the...
Project Update – Wollongong Mazda
Designed by Michael Z. Avramidis Architects, our first of the three stage project at Wollongong Mazda is progressing well. The past two months have seen the completion of demolition works, new blockwork, detailed excavation and construction of the lift shaft...
Project update – Kennards Cardiff
Works are well underway at Kennards Cardiff. The existing storage sheds have been relocated off-site with the first of two ground-floor slabs being poured this week. The next 2 weeks will involve the continuation of screwpiling, Inground works and preparation...
Project update – Buckland Aged Care Services, Stage 5
Our Sydney team have recently completed stage 5 of 10 at Buckland Aged Care Services, Springwood. This stage of the project entailed upgrades to eight existing resident rooms and the addition of a new dining space with floor-to-ceiling glass windows...
Project update – Ground works at St Joseph’s Catholic Primary School Rosebery
Ground works are underway for the brand new school Reitsma is delivering for Sydney Catholic Schools : St Joseph’s Catholic Primary School, Rosebery. The project is being project managed by Impact Group and has been designed by Neeson Murcutt +...
Project Update – St Ives High School : Walkway & Cola
Our Sydney RFM team are progressing well on the new COLA and walkway for St Ives High School, St Ives. This week structural steel was installed over the existing basketball court with ongoing external works taking place on multiple walkways...
Project Update – St George Christian School
Works are progressing well at St George Christian School. Our team poured the level 1 concrete slab for the 3 classroom complex. Works have now started on the installation of formwork for level 2 along with the heritage chapel restoration...
Project Update – Campion College, Toongabbie
Some updated progress shots for the new library and student house dwellings at Campion College, Toongabbie. Our Sydney major works team has managed the installation of internal framing, roof tiles and external brickwork to houses 3, 4, 5 and 6....
Project Update – Central Coast Steiner School, Fountaindale
Good to see the progress made on the new multipurpose centre for Central Coast Steiner School, Fountaindale. This project is really taking shape with the past two weeks seeing the completion of the rammed earth wall structure, installation of roofing,...