Project Update

Project Update
February 8th, 2023
Project Update – McCarrolls Volkswagen Service Centre, Waitara

Great progress is being made on the new service centre at McCarrolls Volkswagen, Waitara. So far the project has involved bulk excavations with formwork and steel fixing. Concrete footings have been poured with shotcrete being used to reinforce the walls. The...

Project Update
January 27th, 2023
Project Update – Mount Carmel Catholic College, Varroville

Great progress is being made by our major works teams at Mount Carmel Catholic School in Varroville. Stage 1 of the project includes work on Block H, Block K1, and Block E. Block H is currently undergoing detailed excavations, with...

Project Update
January 19th, 2023
Project update – St Joseph’s Catholic Primary School Rosebery

The construction of St. Joseph’s Catholic Primary School in Rosebery, Sydney, is moving forward on schedule despite some of the weather challenges of 2022. The foundation structure has been largely completed and work on the ground floor has commenced at...

Project Update
December 16th, 2022
Project update – St George Christian School, Hurstville

Located in the middle of a busy operating school, our Sydney Major works team has achieved great progress recently at St George Christian School, Hurstville. The structural steel roof structure is currently being erected whilst service rough-in and wall framing...

Reitsma News
December 6th, 2022
Project Update – Imagine Learning Centre, Nowra

Works are progressing well for the new  Imagine Learning Centre at Nowra. ( Our second Imagine Centre in the Nowra region ) Last week the ground floor slab was poured with structural framing works taking place for the remainder of...

Project Update
November 24th, 2022
Project update – Campion College Toongabbie ( Library & Houses 3,4,5 & 6 )

Great progress has been made at Campion College, Toongabbie over the last couple of months. Masonry and tiling on houses 3, 4, 5 and 6 has been completed with internal linings ongoing. Masonry and services rough-in is proceeding throughout the...

Project Update
October 28th, 2022
Project Update – Wollongong Mazda

Designed by Michael Z. Avramidis Architects, our first of the three stage project at Wollongong Mazda is progressing well.  The past two months have seen the completion of demolition works, new blockwork, detailed excavation and construction of the lift shaft...

Project Update
October 20th, 2022
Project update – Kennards Cardiff

Works are well underway at Kennards Cardiff. The existing storage sheds have been relocated off-site with the first of two ground-floor slabs being poured this week.  The next 2 weeks will involve the continuation of screwpiling, Inground works and preparation...

Project Update
October 14th, 2022
Project update – Buckland Aged Care Services, Stage 5

Our Sydney team have recently completed stage 5 of 10 at Buckland Aged Care Services, Springwood. This stage of the project entailed upgrades to eight existing resident rooms and the addition of a new dining space with floor-to-ceiling glass windows...

Featured News
October 13th, 2022
Project update – Ground works at St Joseph’s Catholic Primary School Rosebery

Ground works are underway for the brand new school Reitsma is delivering for Sydney Catholic Schools : St Joseph’s Catholic Primary School, Rosebery. The project is being project managed by Impact Group and has been designed by Neeson Murcutt +...

Project Update
October 5th, 2022
Project Update – St Ives High School : Walkway & Cola

Our Sydney RFM team are progressing well on the new COLA and walkway for St Ives High School, St Ives.  This week structural steel was installed over the existing basketball court with ongoing external works taking place on multiple walkways...

Project Update
September 16th, 2022
Project Update – St George Christian School

Works are progressing well at St George Christian School. Our team poured the level 1 concrete slab for the 3 classroom complex. Works have now started on the installation of formwork for level 2 along with the heritage chapel restoration...

Project Update
September 13th, 2022
Project Update – Campion College, Toongabbie

Some updated progress shots for the new library and student house dwellings at Campion College, Toongabbie. Our Sydney major works team has managed the installation of internal framing, roof tiles and external brickwork to houses 3, 4, 5 and 6....

Project Update
August 31st, 2022
Project Update – Central Coast Steiner School, Fountaindale

Good to see the progress made on the new multipurpose centre for Central Coast Steiner School, Fountaindale.  This project is really taking shape with the past two weeks seeing the completion of the rammed earth wall structure, installation of roofing,...

Project Update
August 19th, 2022
Project Complete – University of Newcastle : ATC Building

Our Newcastle RFM team have recently completed the facade upgrade works at the ATC building for the University of Newcastle, Callaghan Campus. These works involved the removal and replacement of the cladded facade. This team completed the project in stages...

Menu