Project Update

Project Update
June 22nd, 2018
Pennant Hills Golf Club, Beecroft NSW

Reitsma has commenced the demolition and ground works for Pennant Hills Golf Club, Beecroft. The structural works are coming together to make way for the new members entry, amenities block and golf shop in the coming weeks. The project is due...

Project Update
June 15th, 2018
Nepean Christian School – Stage 3, Mulgoa NSW

Finishing touches to the latest stage at Nepean Christian School, Mulgoa. The site team are in the process of finalising the building and cleaning/handing over the two building stage. Our client is excited to have had several opportunities to view...

Project Update
May 28th, 2018
St Mark’s Catholic College, Stanhope Gardens NSW

A successful pour for the main hall slab at the St Mark’s project in Stanhope Gardens. Great work and cooperation from all the people involved. Click the article to watch the video.

Project Update
March 23rd, 2018
Covenant Christian School – Stage 3, Belrose NSW

Great progress at Covenant Christian School, Belrose. The roof has now been installed for the new two storey building which includes a administration block and general learning areas. The project is due for completion July, 2018. Reitsma is working alongside...

Project Update
February 2nd, 2017
Crane erected at Mercedes, Artarmon NSW

Good to see the crane is up for the large redevelopment for Mercedes-Benz, Artarmon. Reitsma is working on the new $12 Million dollar service centre which is due for completion later this year.

Project Update
March 14th, 2016
Level 3 Concrete Pour – OLMC, Parramatta NSW

Reitsma recently undertook the final concrete deck pour at OLMC, Parramatta. Over 450 m2 of concrete in varying strengths was poured in just over 12 hours. The concrete roof will function as a rooftop playground for the school once complete.

Project Update
December 4th, 2014
Oran Park Anglican Church, Oran Park NSW

Working along side NBRS + Partners, construction works have been progressing well at the new Anglican church in Oran Park. The project will be a bold architectural statement with a large amount of exposed off form concrete finishing.  Recently the...

Project Update
September 19th, 2014
Timelapse – Concrete Pour: Marist College, Eastwood NSW

Check out the Timelapse of the Concrete Pour at Marist College, Eastwood.

Project Update
September 17th, 2014
Marist College, Eastwood NSW

Over 600m3 of concrete has just been poured to the roof top playing courts at Marist College, Eastwood. Well done to the Reitsma team involved in making this happen.